9.2 Delayed Tests
9.2 延误的试验
If the Tests on Completion are being unduly delayed by the Employer, Sub-Clause 7.4 [Testing] (fifth paragraph) and/or Sub-Clause 10.3 [Interference with Tests on Completion] shall be applicable.
如果雇主不当地延误竣工试验,雇主可通知承包商,要求在接到通知后21天内进行竣工试验。承包商应在上述期限内的某日或某几日内进行竣工试验,并将该日期通知雇主。
If the Tests on Completion are being unduly delayed by the Contractor, the Employer may by notice require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Employer.
如果承包商未在规定的21天内进行竣工试验,雇主人员可自行进行这些试验。试验的风险和费用应由承包商承担。这些竣工试验应被视为是承包商在场时进行的,试验结果应认为准确,予以认可。
If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employer’s Personnel may proceed with the Tests at the risk and cost of the Contractor. These Tests on Completion shall then be deemed to have been carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate.
9.3 Retesting
9.3 重新试验
If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause 7.5 [Rejection] shall apply, and the Employer or the Contractor may require the failed Tests, and Tests on Completion on any related work, to be repeated under the same terms and conditions.
如果工程或分项工程未能通过竣工试验,应适用第7.5款[拒收]的规定,雇主或承包商可要求按相同的条款和条件,重新进行此项未通过的试验和相关工程的竣工试验。